The government expects domestic oil and gas production to pick up in the next 4-5 years as several steps taken in the recent past begin to bear fruit in an industry typically characterised by long gestation periods, The Hindu has learnt.

According to an analysis by the Ministry of Petroleum and Natural Gas, the current contraction in domestic oil and gas production is due to factors that took place more than a decade ago.

However, since then, the government has taken steps such as increasing drilling and exploration to record levels, changing laws and rules to provide stable terms to explorers, and opening new avenues for exploration.

“The steps taken in the last few years — new acreage, record drilling, deepwater wells and the revival of Mumbai High — will start showing up in production over the next three to four years,” the note asserted. “That is the nature of this sector: the decisions of one decade decide the output of the next.”

Upstream profits now used for exploration

The note also argues that now, unlike earlier, the profits of oil and gas companies upstream companies like ONGC and Oil India are being used to fund exploration rather than subsidies.

“Until 2015, ONGC and Oil India were made to fund a large share of the subsidy on diesel, LPG and kerosene, through discounts on the crude they sold to oil marketing companies,” the note said.

According to data with the Ministry, ONGC paid ₹49,421 crore towards this subsidy in 2012-13 against a profit of ₹20,926 crore, and in 2013-14 paid ₹56,384 crore towards this subsidy against a net profit of ₹22,095 crore.

“In both years ONGC gave away more than twice what it earned,” the note said. “Money that should have gone into finding new oil and gas went into keeping retail prices down. This burden was ended from 2015-16. ONGC now keeps its earnings and has sharply raised its spending on exploration.”

No new exploration until 2016

According to the latest data on the Index of Core Industries, the oil and gas sectors have contracted continuously for 22 and 28 months, respectively.

“In this sector it takes five to ten years to go from awarding a block to first production,” a note prepared by the Ministry and accessed by The Hindu said. “Output in 2026 is the result of what was, and was not, done a decade ago.

“After the ninth New Exploration Licensing Policy (NELP) round was launched in 2010, no new exploration round was offered until 2016,” it added. “The fields producing today were not replaced by new ones in that period, and the effect is still being felt.”

Mature fields seeing falling output

The Ministry also stated that mature oil and gas fields generally lose 7-8% of their output every year as reservoir pressure falls and that most of India’s current production comes from such fields. On the other hand, new wells, enhanced recovery, and field redevelopment are making up much of the loss.

As a result, crude oil output fell 4.1% in October 2026, a lower rate of decline than what is generally seen, even though the fields are decades old. Further, the note added that the decline is being seen more among private companies rather than public sector ones.

“The steepest fall has come from private producers, whose mature fields have seen double-digit declines over the past year,” it said.

Steps to increase production

The note acknowledges these issues and says that lasting growth has to come from deepwater exploration, where the time from discovery to production is long. Towards this, the government has opened about 1 million square kilometres of areas earlier marked as ‘No-Go’, and deepwater blocks are being awarded in it for exploration in stages.

The Samudra Manthan mission has committed ₹84,084 crore in its first phase to seismic surveys, more than 60 deepwater wells and shared offshore infrastructure, with the Government bearing up to half the cost of a deepwater well.

The government data also shows that ONGC drilled 501 wells in 2025-26, 100 of them exploratory, after drilling 578 in 2024-25, the highest number in 35 years. ONGC made three new offshore discoveries in 2025-26 and added more reserves than it produced, with a reserve replacement ratio of 1.17, the note added.

ONGC drilled four ultra-deepwater wells in the Andaman basin in 2025-26 and began a deepwater well in the Mahanadi basin in July 2026.

Further, the note said that the Oilfields (Regulation and Development) Amendment Act, 2025 and the rules under it have given investors stable and long-term terms of doing business.

The other large public sector upstream company, Oil India, struck gas in two of its three wells off the east coast of the Andaman Islands: Sri Vijayapuram-2 in September 2025 and Sri Vijayapuram-3 in June 2026.

Published – November 23, 2026 07:30 pm IST